Construction on the roundabout at the intersection of Highway 20 and Memorial Trail, is beginning soon. When phase 1 begins, the intersection will become a right in right out only.

This change along with detours is tentatively scheduled for May 6. Please plan for alternate routes. 

Phase 1: Dates TBD

Starting April 22

  • Hydro vacuum work on underground crossings

Expected early May

  • Memorial Trail may require full closure for up to 2 days at certain times
  • Fortis line move
  • No left turns:
    • From Highway 20 northbound lane onto westbound Memorial Trail
    • From Highway 20 southbound lane onto eastbound Township Road 384
    • From Memorial Trail eastbound lane onto northbound Highway 20
    • From Township Road 384 westbound lane onto southbound Highway 20

Phase 2: Dates TBD, expected start mid June, 2024

  • Township Road 384 CLOSED at Highway 20
  • Memorial Trail may require full closure for up to 2 days at certain times
  • No left turns:
    • From Highway 20 northbound lane onto westbound Memorial Trail
    • From Highway 20 southbound lane onto eastbound Township Road 384
    • From Memorial Trail eastbound lane onto northbound Highway 20